Amended Exploration Update Dalmas & Hiver Lithium Projects
Released
Released
Announcement PDF
ASX Announcement
03 November 2023
EXPLORATION UPDATE FOR DALMAS AND HIVER LITHIUM
PROJECTS IN QUEBEC
Lightning Minerals (L1M or the Company) is pleased to announce that it has completed its initial
exploration program at its Dalmas and Hiver Projects in the James Bay region of Quebec, Canada. The
program has confirmed historical reports of outcropping pegmatitic lithologies at both the Dalmas and
Hiver project areas.
HIGHLIGHTS
o
First pass ground reconnaissance works are now successfully complete for the
Dalmas and Hiver projects prior to the onset of the Canadian winter
o
Historic reports of pegmatites have been confirmed during the field reconnaissance,
these pegmatites are broadly coincident with targets identified during recent
Multispectral analysis1
o
Follow up exploration programs are now being developed with a focus on reviewing
existing geophysical data across the project areas and defining target areas for
further exploration targeting
Following the execution of a binding agreement to acquire the Dalmas and Hiver Projects2, the
Company has now rapidly completed its first reconnaissance phase exploration prior to the onset of
the Canadian winter.
As outlined in ASX announcement 30 August 2023, 165 multispectral targets were identified over the
company’s Dalmas and Hiver projects, with 113 targets at Dalmas and 52 targets at Hiver. The
reconnaissance field program focussing on these areas and has successfully identified multiple
instances of pegmatite outcrop, as well as pegmatite boulders at surface.
Lightning Minerals’ Managing Director Alex Biggs said, “Confirmation of pegmatite lithologies at
both Dalmas and Hiver is a positive indicator for our future exploration in Canada. It is important that
the Company has taken its first step quickly and effectively by confirming the target areas that have
been previously identified. We know the James Bay region is prolific as a lithium district and initial
indications at Dalmas and Hiver suggest that potential exists. Our next step will be to evaluate existing
geophysical surveys that may define geological trends of sub-cropping pegmatite structures across
both projects. The Company continues to employ a diligent and structured approach to its exploration
across all its projects with a view to defining drill targets for potential discovery. Having projects in two
of the most prospective lithium regions globally significantly increases our chances of that. We look
forward to keeping you updated on our progress”.
Note 1: The geochemical nature of the pegmatitic geological outcrop is currently unknown and the presence of pegmatitic lithologies does
not necessarily indicate the presence of lithium, tantalum or caesium mineralisation. Only laboratory chemical assays can determine the
presence and grade of any mineralisation.
1ASX Announcement 30 August 2023, 2ASX Announcement 29 September 2023
Level 6, 505 Little Collins Street, Melbourne VIC 3000 | admin@lightningminerals.com.au | www.lightningminerals.com.au | (08) 9429 8806
RECONNAISSANCE WORK PROGRAM AND TARGETS
The Dalmas and Hiver Projects are located in the James Bay region of Quebec; approximately 150km to
the east of Patriot Battery Metals’ (ASX: PMT) Corvette lithium project and 45km to the east of Winsome
Resources’ (ASX: WR1) Adina lithium project. Recent satellite multispectral analysis identified multiple
target signatures1 which are thought to represent geochemically suitable sites for pegmatite
emplacement, as they have a similar spectral character to pegmatite occurrences in the region.
Of the 165 multispectral targets, 113 are located within the Dalmas project and the remaining 52 targets
within the Hiver Project. These targets formed seven clustered areas across the two projects that
required follow up field investigation. Additionally, historic Quebec Geological Survey records report
outcrop mapping information that claimed outcropping pegmatitic lithologies may occur at three of
the four priority clustered target areas.
A reconnaissance mapping and rock sampling program was then developed and conducted during
late October. The program was managed by the experienced Quebec-based company IOS Geosciences
(IOS). Preliminary indications from the field reconnaissance have confirmed the presence of
pegmatites within both the Dalmas and Hiver projects. Figure 1 and 2 display field locations where both
pegmatitic outcrop and pegmatite boulders have been recorded; initial visual assessment by field
geologists suggest the mineral assemblages present are commonly quartz-feldspar-biotite.
Preliminary details of each mapping and sample location are included in Appendix 2. The geochemistry
of these pegmatites is yet to be quantified via laboratory analysis of 32 samples taken, assay results are
expected to be returned within an 8 week period.
Figure 1: Pegmatite outcrop and boulders mapped within the Dalmas Project (NAD 83/UTM Z18N)
Level 6, 505 Little Collins Street, Melbourne VIC 3000 | admin@lightningminerals.com.au | www.lightningminerals.com.au | (08) 9429 8806
Figure 2: Pegmatite outcrop and boulders mapped within the Hiver Project (NAD 83/UTM Z18N)
Figure 3 and 4: Left: Pegmatite outcrop within the Dalmas Project (317026mE, 5943450mN, WGS
84/UTMZ19N), and Right: Large Quartz Feldspar Biotite Pegmatite Boulder located at 319995mE,
5940922mN, WGS 84/UTMZ19N.
Level 6, 505 Little Collins Street, Melbourne VIC 3000 | admin@lightningminerals.com.au | www.lightningminerals.com.au | (08) 9429 8806
Figure 5 and 6: Left: Pegmatite containing potential beryl (±Apatite?) mineral within Dalmas project
(Pen lid for scale, 316859mE, 5943604mN, WGS 84/UTMZ19N), Right: Quartz Feldspathic pegmatite sample
taken from Hiver project (302519mE, 5995547mN, WGS 84/UTMZ19N)
The field team have identified potential Beryllium bearing minerals in outcropping pegmatites, (Green
mineral shown in red circle in Figure 5) which is considered a positive exploration indicator.
A total of 32 rock chip samples have been collected over the course of the program. Mineralogical
descriptions of each sample remain pending and are expected with delivery of the final field report.
Samples have been submitted for analysis for a full suite of elements through Activation Laboratories
Ltd. Upon receipt of the results the geochemical signature of the pegmatites at Dalmas and Hiver these
results can then be scrutinised and appropriate elemental ratio applied. This data will prove crucial in
understanding the most prospective areas to concentrate future exploration for future follow up field
activities.
The early multispectral targets generated from desktop analysis have proven to be a valuable means
for the initial targeting of pegmatites at the Dalmas and Hiver projects. The successful completion of
the reconnaissance program and the confirmation of pegmatites prior to the onset of winter is
considered a significant step in exploration progress. The focus over the coming months will be a review
of all previous geological and geophysical data available for the area that may further accelerate
exploration efforts.
Note: Any visual estimates of mineral abundance should never be considered a proxy or substitute for laboratory analyses where
concentrations or grades are the factor of principal economic interest. Visual estimates also potentially provide no information regarding
impurities or deleterious physical properties relevant to valuations.
ABOUT THE PROJECTS AND QUEBEC AS A SIGNIFICANT LITHIUM REGION
Quebec is quickly becoming one of the world’s leading lithium regions, particularly the James Bay
district which hosts multiple large scale lithium projects including:
•
•
Patriot Battery Metals’ (ASX: PMT) Corvette lithium project3 consisting of 109.2Mt @ 1.42% Li20
Inferred
Nemaska Lithium’s (TSX: NMX) Whabouchi lithium project4 with 55.7Mt @ 1.4% Li20 consisting of
38.5Mt @ 1.45% Li20 Measured and Indicated and 17.2Mt @ 1.29% Li20 Inferred
Level 6, 505 Little Collins Street, Melbourne VIC 3000 | admin@lightningminerals.com.au | www.lightningminerals.com.au | (08) 9429 8806
•
•
Critical Elements’ (TSX.V: CRE) Rose lithium project5 with 34.2Mt @ 0.9% Li20 consisting of 31.5Mt @
0.91% Li20 Indicated and 2.7Mt @ 0.77% Li20 Inferred
Sayona Mining’s (ASX: SYA) Moblan lithium project6 with 51.4Mt @ 1.30% Li20 Measured, Indicated
and Inferred
•
Allkem’s (ASX: AKE) James Bay lithium project7 with 54.3Mt @ 1.30% Li20 Indicated and 55.9Mt @
1.29% Li20 Inferred
•
Winsome Resources’ (ASX: WR1)8 who are exploring multiple lithium projects in the region
Figure 7: Dalmas and Hiver project locations, James Bay, Quebec
REFERENCES
ASX Announcement 30 August 2023
ASX Announcement 29 September 2023
3
Patriot Battery Metals (PMT) ASX Announcement 31 July 2023
4
Nemaska Lithium’s TSX Announcement 09 August 2019
5
Critical Element’s TSX.V Announcement 27 July 2022
6
Sayona Mining’s ASX Announcement 17 April 2023
7
Allkem’s ASX Announcement 11 August 2023
8
Winsome Resources (WR1) ASX Announcement 01 August 2023
1
2
This announcement has been approved for release by the Board of Directors.
-ends
Level 6, 505 Little Collins Street, Melbourne VIC 3000 | admin@lightningminerals.com.au | www.lightningminerals.com.au | (08) 9429 8806
ABOUT LIGHTNING MINERALS
Lightning Minerals is a mineral exploration company, listed on the Australian Stock Exchange (ASX:L1M) and focused on the
exploration of critical minerals and lithium at its tenements across Western Australia. The Company’s flagship Dundas project is
located in the prolific Dundas region of Western Australia. The Company also has other projects in Western Australia, Mt Jewell,
Mt Bartle and Mailman Hill prospective for base metals and critical minerals.
FORWARD LOOKING STATEMENTS
Information included in this release constitutes forward-looking statements. Often, but not always, forward looking statements
can generally be identified by the use of forward-looking words such as “may”, “will”, “expect”, “intend”, “plan”, “estimate”,
“anticipate”, “continue”, and “guidance”, or other similar words and may include, without limitation, statements regarding plans,
strategies and objectives of management, anticipated production or construction commencement dates and expected costs or
production outputs.
Forward looking statements inherently involve known and unknown risks, uncertainties and other factors that may cause the
Company’s actual results, performance and achievements to differ materially from any future results, performance or
achievements. Relevant factors may include, but are not limited to, changes in commodity prices, foreign exchange fluctuations
and general economic conditions, increased costs and demand for production inputs, the speculative nature of exploration and
project development, including the risks of obtaining necessary licences and permits and diminishing quantities or grades of
reserves, political and social risks, changes to the regulatory framework within which the Company operates or may in the future
operate, environmental conditions including extreme weather conditions, recruitment and retention of personnel, industrial
relations issues and litigation.
Forward looking statements are based on the Company and its management’s good faith assumptions relating to the financial,
market, regulatory and other relevant environments that will exist and affect the Company’s business and operations in the
future. The Company does not give any assurance that the assumptions on which forward looking statements are based will
prove to be correct, or that the Company’s business or operations will not be affected in any material manner by these or other
factors not foreseen or foreseeable by the Company or management or beyond the Company’s control.
Although the Company attempts and has attempted to identify factors that would cause actual actions, events or results to differ
materially from those disclosed in forward looking statements, there may be other factors that could cause actual results,
performance, achievements or events not to be as anticipated, estimated or intended, and many events are beyond the
reasonable control of the Company. Accordingly, readers are cautioned not to place undue reliance on forward looking
statements. Forward looking statements in these materials speak only at the date of issue. Subject to any continuing obligations
under applicable law or any relevant stock exchange listing rules, in providing this information the Company does not undertake
any obligation to publicly update or revise any of the forward-looking statements or to advise of any change in events, conditions
or circumstances on which any such statement is based.
COMPETENT PERSONS STATEMENT
The information contained herein that relates to exploration results is based on information compiled or reviewed by Mr Jarrad
Woodland, who is a Competent Person and a member of the Australasian Institute of Mining and Metallurgy. Mr Woodland is a
full-time employee of the company. Mr Woodland has sufficient experience which is relevant to the style of mineralisation and
types of deposit under consideration and to the activity which he is undertaking to qualify as a Competent Persons as defined in
the 2012 Edition of the ‘Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves’. Mr
Woodland consents to the inclusion of his name in the matters based on the information in the form and context in which it
appears. Mr Woodland holds options in Lightning Minerals.
Lightning Minerals engaged IOS Geosciences (IOS) to execute the prospecting and exploration work described in this news
release. IOS has an experienced team of explorers based in Saguenay and is managing several projects in the James Bay region.
This report contains information related to exploration results and is based on preliminary information and data compiled or
reviewed by IOS under the supervision of Mr. Hugues Longuepee, who is classified as a Professional Geoscientist (P. Geo) with
the respective professional regulatory body, the Order of Geologists of Quebec. Mr. Longuepee has also reviewed this new release.
REFERENCES TO PREVIOUS ANNOUNCEMENTS
The Company confirms that it is not aware of any new information or data that materially affects the information included in the
original market announcements, and that all material assumptions and technical parameters have not materially changed. The
Company also confirms that the form and context in which the Competent Person’s findings are presented have not been
materially modified from the original market announcement.
Level 6, 505 Little Collins Street, Melbourne VIC 3000 | admin@lightningminerals.com.au | www.lightningminerals.com.au | (08) 9429 8806
APPENDIX 1: JORC CODE 2012 TABLE 1 CRITERIA
The Table below summarises the assessment and reporting criteria used for exploration results for the Dalmas and Hiver Exploration Projects and reflects the guidelines in Table 1 of The Australasian
Code for the Reporting of Exploration Results, Mineral Resources and Ore Reserves (The JORC 2012 Code).
SECTION 1 - SAMPLING TECHNIQUES AND DATA
Criteria
JORC Code explanation
Sampling techniques
Nature and quality of sampling (eg cut channels, random chips, or specific
specialised industry standard measurement tools appropriate to the
minerals under investigation, such as down hole gamma sondes, or
handheld XRF instruments, etc). These examples should not be taken as
limiting the broad meaning of sampling.
Include reference to measures taken to ensure sample representivity and
the appropriate calibration of any measurement tools or systems used.
Aspects of the determination of mineralisation that are Material to the
Public Report.
In cases where ‘industry standard’ work has been done this would be
relatively simple (eg ‘reverse circulation drilling was used to obtain 1 m
samples from which 3 kg was pulverised to produce a 30 g charge for fire
assay’). In other cases more explanation may be required, such as where
there is coarse gold that has inherent sampling problems. Unusual
commodities or mineralisation types (eg submarine nodules) may warrant
disclosure of detailed information.
Drill type (eg core, reverse circulation, open-hole hammer, rotary air
blast, auger, Bangka, sonic, etc) and details (eg core diameter, triple or
standard tube, depth of diamond tails, face-sampling bit or other type,
whether core is oriented and if so, by what method, etc).
Method of recording and assessing core and chip sample recoveries and
results assessed.
Measures taken to maximise sample recovery and ensure representative
nature of the samples.
Whether a relationship exists between sample recovery and grade and
whether sample bias may have occurred due to preferential loss/gain of
fine/coarse material.
Whether core and chip samples have been geologically and
geotechnically logged to a level of detail to support appropriate Mineral
Resource estimation, mining studies and metallurgical studies.
Whether logging is qualitative or quantitative in nature. Core (or costean,
channel, etc) photography.
The total length and percentage of the relevant intersections logged.
Drilling techniques
Drill sample recovery
Logging
Commentary
•
•
•
Rock chip sampling is associated with the reconnaissance mapping and sampling program which aimed to confirm historical
pegmatite reports, by both locating both previous and sampling pegmatite outcrops or boulders.
Work described in the release has involved review of the publicly available datasets which are available through the
‘Geomining Information System of Quebec’ - sigeom.mines.gouv.qc.ca
Ministère des Resources Naturelles et des Forêts (MERN), the Quebec geological survey (QGS), documents historical
mapping over the Hiver and Dalmas Project areas; and surrounding region with rock descriptions publicly available.
•
No assay data is available for MERN samples/mapping points.
•
No drilling is reported.
•
No drill samples have been taken.
•
•
•
•
No drilling completed.
Mineral percentage bins of surface samples are as follows - Primary Minerals (Major >30%), Secondary Minerals (Minor
>5% and <30%), Accessory Minerals (Trace <5%). These are preliminary visual estimates only, the final field report which
remains pending will contain more accurate geological descriptions including geochemical assay data.
Geological observations are both preliminary and qualitative. The information contained within describes only dominant
outcrop lithologies at discreet locations, and minerals of interest.
All data is stored in digital format for use in GIS software packages.
Level 6, 505 Little Collins Street, Melbourne VIC 3000 | admin@lightningminerals.com.au | www.lightningminerals.com.au | (08) 9429 8806
Sub-sampling techniques
and sample preparation
Quality of assay data and
laboratory tests
Verification of sampling
and assaying
Location of data points
Data spacing and
distribution
Orientation of data in
relation to geological
structure
If core, whether cut or sawn and whether quarter, half or all core taken.
If non-core, whether riffled, tube sampled, rotary split, etc and whether
sampled wet or dry.
For all sample types, the nature, quality and appropriateness of the
sample preparation technique.
Quality control procedures adopted for all sub-sampling stages to
maximise representivity of samples.
Measures taken to ensure that the sampling is representative of the in
situ material collected, including for instance results for field
duplicate/second-half sampling.
Whether sample sizes are appropriate to the grain size of the material
being sampled.
The nature, quality and appropriateness of the assaying and laboratory
procedures used and whether the technique is considered partial or
total.
For geophysical tools, spectrometers, handheld XRF instruments, etc, the
parameters used in determining the analysis including instrument make
and model, reading times, calibrations factors applied and their
derivation, etc.
Nature of quality control procedures adopted (eg standards, blanks,
duplicates, external laboratory checks) and whether acceptable levels of
accuracy (ie lack of bias) and precision have been established.
The verification of significant intersections by either independent or
alternative company personnel.
The use of twinned holes.
Documentation of primary data, data entry procedures, data verification,
data storage (physical and electronic) protocols.
Discuss any adjustment to assay data.
Accuracy and quality of surveys used to locate drill holes (collar and
down-hole surveys), trenches, mine workings and other locations used in
Mineral Resource estimation.
Specification of the grid system used.
Quality and adequacy of topographic control.
Data spacing for reporting of Exploration Results.
Whether the data spacing and distribution is sufficient to establish the
degree of geological and grade continuity appropriate for the Mineral
Resource and Ore Reserve estimation procedure(s) and classifications
applied.
Whether sample compositing has been applied.
Whether the orientation of sampling achieves unbiased sampling of
possible structures and the extent to which this is known, considering the
deposit type.
If the relationship between the drilling orientation and the orientation of
key mineralised structures is considered to have introduced a sampling
bias, this should be assessed and reported if material.
•
•
•
•
•
•
•
•
•
•
•
•
•
•
Sampling is at the discretion of field geologists undertaking the geological reconnaissance activities.
At this early stage of exploration discretionary grab samples are considered appropriate.
No QAQC processes have been utilised at this early stage of exploration.
No assay data or laboratory test work is reported.
No data verification has occurred.
The company has verified the presence of historically reported outcrop lithologies during the reconnaissance phase of
exploration works.
All geological maps utilising NAD83 / UTM zone 18N are sufficiently annotated.
All geological locations utilising WGS84 / UTM zone 19N are sufficiently annotated.
All reported locations are assumed to have a +/- 10m accuracy via use of handheld GPS instruments.
Data points are guided by field outcrops instead of regular spacing.
Exploration data contained within is not appropriate for calculating Mineral Resources. Insufficient exploration has been
completed at this stage to warrant such calculations.
No compositing of results has been reported in this announcement.
Field observation points are guided by outcrop location instead of specific orientation.
No relationship between outcrop mapping sites is known.
Level 6, 505 Little Collins Street, Melbourne VIC 3000 | admin@lightningminerals.com.au | www.lightningminerals.com.au | (08) 9429 8806
Sample security
The measures taken to ensure sample security.
•
Audits or reviews
The results of any audits or reviews of sampling techniques and data.
•
Field samples have been collected and stored by IOS Geosciences, under the supervision of Mr. Hugues Longuepee
P.Geo.. Mr. Longuepee, is QP and a Member of the Ordre des geologues du Quebec.
No audits or reviews have been undertaken.
SECTION 2 - REPORTING OF EXPLORATION RESULTS
Criteria
JORC Code explanation
Mineral tenement and
land tenure status
Type, reference name/number, location and ownership including
agreements or material issues with third parties such as joint ventures,
partnerships, overriding royalties, native title interests, historical sites,
wilderness or national park and environmental settings.
The security of the tenure held at the time of reporting along with any
known impediments to obtaining a licence to operate in the area.
Commentary
•
•
•
•
•
•
•
•
Exploration done by other Acknowledgment and appraisal of exploration by other parties.
parties
•
The Hiver and Dalmas projects are located in the James Bay Region of Quebec, Canada.
The Hiver and Dalmas projects are centered at approximately 54°03’20”N, 72°01’57”W, and 53°36’01”N, 71°43’18”W
respectively.
The Hiver and Dalmas Project are 100% owned by Lithium Rabbit Quebec Pty Ltd.
Lightning Minerals Ltd signed a binding letter of intent on 11th August 2023 to acquire two project areas, Dalmas and Hiver
in the James Bay region of Quebec, Canada.
The Dalmas project is comprised of 92 mining claims totaling 4,707Ha
The Hiver project is comprised of 62 mining claims totaling 3137Ha
Lithium Rabbit Quebec Pty Ltd retains a 2.0% Net Smelter Royalty, of which 1.0% may be bought back by the Company at
any time for A$1.0 million. The NSR is applicable across both projects.
All tenements are in good standing and are presented in this announcement.
Geological datasets were sourced from Ministère des Resources Naturelles et des Forêts (MERN), the Quebec geological
survey.
•
No other data by prior explorers is known to the company.
Geology
Deposit type, geological setting and style of mineralisation.
•
The mineralisation style sought at the Dalmas and Hiver Projects is Lithium bearing pegmatites.
Drill hole Information
A summary of all information material to the understanding of the
exploration results including a tabulation of the following information for all
Material drill holes:
o
easting and northing of the drill hole collar
o
elevation or RL (Reduced Level – elevation above sea
level in metres) of the drill hole collar
o
dip and azimuth of the hole
o
down hole length and interception depth
o
hole length.
If the exclusion of this information is justified on the basis that the
information is not Material and this exclusion does not detract from the
understanding of the report, the Competent Person should clearly explain
why this is the case.
In reporting Exploration Results, weighting averaging techniques, maximum
and/or minimum grade truncations (eg cutting of high grades) and cut-off
grades are usually Material and should be stated.
•
No drillholes are reported.
•
No exploration results have been reported.
Data aggregation
methods
Level 6, 505 Little Collins Street, Melbourne VIC 3000 | admin@lightningminerals.com.au | www.lightningminerals.com.au | (08) 9429 8806
Relationship between
mineralisation widths
and intercept lengths
Diagrams
Balanced reporting
Other substantive
exploration data
Further work
Where aggregate intercepts incorporate short lengths of high grade results
and longer lengths of low grade results, the procedure used for such
aggregation should be stated and some typical examples of such
aggregations should be shown in detail.
The assumptions used for any reporting of metal equivalent values should be
clearly stated.
These relationships are particularly important in the reporting of Exploration
Results.
If the geometry of the mineralisation with respect to the drill hole angle is
known, its nature should be reported.
If it is not known and only the down hole lengths are reported, there should
be a clear statement to this effect (eg ‘down hole length, true width not
known’).
Appropriate maps and sections (with scales) and tabulations of intercepts
should be included for any significant discovery being reported These should
include, but not be limited to a plan view of drill hole collar locations and
appropriate sectional views.
Where comprehensive reporting of all Exploration Results is not practicable,
representative reporting of both low and high grades and/or widths should
be practiced to avoid misleading reporting of Exploration Results.
Other exploration data, if meaningful and material, should be reported
including (but not limited to): geological observations; geophysical survey
results; geochemical survey results; bulk samples – size and method of
treatment; metallurgical test results; bulk density, groundwater,
geotechnical and rock characteristics; potential deleterious or
contaminating substances.
The nature and scale of planned further work (eg tests for lateral extensions
or depth extensions or large-scale step-out drilling).
Diagrams clearly highlighting the areas of possible extensions, including the
main geological interpretations and future drilling areas, provided this
information is not commercially sensitive.
•
No drill results are reported.
•
Appropriate two-dimensional plans have been included in the body of this announcement.
•
•
•
•
•
•
•
No exploration results are reported.
Lightning Minerals is committed to accurately detailing the results from any exploration activities, and reporting results in a
balanced manner.
Lightning Minerals Ltd engaged IOS Geosciences during October 2023.
IOS Geosciences have completed field reconnaissance as planned and reported preliminary results as contained herein.
All pegmatite lithologies mapped within the project areas require geochemical analysis to ascertain if a relationship to
relevant mineralisation processes are present. The presence of pegmatites in outcrop and boulders alone is not sufficient
to assume the presence of mineralisation.
As detailed in text.
Exploration efforts will continue with a consolidation and review of all previous geological and geophysical data available
for the project areas.
Level 6, 505 Little Collins Street, Melbourne VIC 3000 | admin@lightningminerals.com.au | www.lightningminerals.com.au | (08) 9429 8806
APPENDIX 2 - TABLE 1: REPORTING VISUAL ESTIMATES OF MINERALISATION
Project
Sample ID
Dalmas
-
Hiver
-
Geology/Comments
No lithium mineralisation is reported within samples taken from the Dalmas project. At this early stage of exploration all samples represent exploration stage
sampling to understand the background geochemistry of reported pegmatites.
No lithium mineralisation is reported within samples taken from the Hiver project. At this early stage of exploration all samples represent exploration stage
sampling to understand the background geochemistry of reported pegmatites.