Caravel Copper Project Development Milestones

Completed Upcoming
Done
Nov 2023
Resource update
3.03Mt Cu confirmed, Australia's largest undeveloped deposit
Done
May 2024
ERD lodged with EPA
Major permitting milestone, environmental review submitted
Done
Oct 2024
Water agreement signed
Saline borefield secured approx. 60km west of site
Done
Apr 2025
Flowsheet finalised
SAG mill selected after 4 years of testing, 86% Cu recovery
Done
Aug 2025
Primero appointed
NRW Holdings subsidiary engaged to lead the DFS
Done
Nov 2025
Mine plan updated
25-year, 30Mtpa operation confirmed with 1.22:1 strip ratio
Done
Nov 2025
Adani MOU signed
Life-of-mine offtake with potential strategic equity investment
Done
Feb 2026
European ECA support
Preliminary export credit agency backing secured
Next
Mid 2026
DFS complete
Definitive Feasibility Study completion for FID
Upcoming
2026
ERD public review
WA environmental public comment period opens
Upcoming
2026
FID
Final Investment Decision post government approvals
Upcoming
2027 to 2028
Construction
18 to 24 month build targeting 65k-71ktpa Cu production